Cortland · State Agency / ESD
SUNY Cortland New 4-Story Apartment-Style Residence Hall
Pashley Drive & Folmer Drive (near Tompkins Street Entrance / 3739 Stratton Drive), Cortland, NY 13045
- Student Beds
- 220
- Sq ft
- 74,200
- Cost
- $46M
Cortland, NY • Central NY
16 Neubig Road, SUNY Cortland, Cortland, NY 13045
Last updated on Nov 17, 2026
Project #041046-02 (Contract #D007082). Comprehensive renovation of Corey Union student center on the SUNY Cortland campus, including a new geothermal wellfield at the south end of the Bowers Hall parking lot. Procurement Status lists a $57,541,000 estimated construction cost, within an $80,517,000 total capital program budget in the SUNY 2026/27 Capital Program Plan. Construction Management contract ($3,155,679, term 10/12/2026–10/12/2031) awarded to Jacobs Project Management Co. Pre-closure event relocation planning underway per August 2026 campus update.
State University Construction Fund (SUCF)· Nov 17, 2026
Modernizes student union gathering spaces, dining, student government offices, and event facilities while upgrading building mechanical systems.
Campus updates note relocation of large campus events during building closure and installation of a geothermal borefield in the Bowers Hall parking lot; 30% MWBE and 6% SDVOB goals apply to Contract #D007082.
Not addressed in cited procurement tables or campus facilities updates.