White Pine Commerce Park, Route 31 & Caughdenoy Road, Clay, NY 13041

Clay, NY • Central NY

Micron Semiconductor Manufacturing Campus

White Pine Commerce Park, Route 31 & Caughdenoy Road, Clay, NY 13041

Under Construction

Last updated on Nov 4, 2026

What is it? · Identity & scale

Project type
Industrial
Review stage
Under Construction
Stories
4
Acreage
1,377 ac

Who & what? · Context & documents

Developer / applicant entity
Micron Technology, Inc.
Estimated investment / project cost
$100.0B
Reviewing board
Multiple / Multi-Agency
Architectural consultant
Jacobs

Site notes

Largest private investment in NY history. Multi-decade 1,377-acre DRAM semiconductor complex at White Pine Commerce Park featuring four 600,000 SF cleanrooms (~2.4M SF cleanroom total), on-site water recycling, 345kV substation, and rail spur. Generates ~9,000 direct and ~40,000 indirect jobs. Type I Action with review. OCIDA's October 21, 2025 model for project 3101-23-07A uses a $51.5B scope and 4,514 jobs, separate from the $100B multidecade campus vision. It projects $84,501,999 payments over 49 years versus $368,384,225 without ; $283,882,226 property-tax relief plus $1.76B sales-tax assistance. Modeled, not actual, amounts. Signed agreements and benefit-use reports remain unverified. Clay's Fab 1 presentation separates $20M payments over three years from $10M dedicated Green CHIPS spending. 's $500M community fund comprises $250M Micron, $100M state and remaining partner fundraising over 20 years.

Public record & decisions

Applicant Claims

Historic job creation (~9,000 direct, ~40,000 supply chain); $100B catalytic economic investment; $30M funding local parks, public safety, and road upgrades; regional infrastructure modernization.

Staff / Agency Concerns

1,300+ acre land disturbance; major traffic increases along Route 31 and I-81; immense electric and municipal water utility load; rapid suburban sprawl pressure on regional services.

Public Testimony

Overwhelming regional economic excitement balanced with active public hearing debate regarding local union labor commitments, environmental safeguards, and property tax abatement terms.

Earlier record notes · source attribution pending

Older entries may combine applicant, agency, board and public comments. They are not classified as verified testimony.

Historic job creation (~9,000 direct, ~40,000 supply chain); $100B catalytic economic investment; $30M funding local parks, public safety, and road upgrades; regional infrastructure modernization.

1,300+ acre land disturbance; major traffic increases along Route 31 and I-81; immense electric and municipal water utility load; rapid suburban sprawl pressure on regional services.

Overwhelming regional economic excitement balanced with active public hearing debate regarding local union labor commitments, environmental safeguards, and property tax abatement terms.

The story behind it

Researched Oct 14, 2026 · Medium confidenceSupported by public records, with some gaps or single-source details.

Micron's $100 billion figure describes a multidecade campus vision; the county's analysis and Clay's host agreement each cover narrower scopes, so the numbers should not be added together.

History

Different numbers describe different parts of Micron.

Micron's $100 billion campus vision is a multidecade plan. OCIDA's October 2025 tax analysis covers a separate $51.5 billion project scope. It estimates $84.5 million in property-tax substitute payments over 49 years, compared with $368.4 million without the . These are projections, not payments already collected (OCIDA project summary, Oct. 21, 2025).

Clay's Fab 1 host arrangement also has two parts: $20 million in payments over three years and $10 million in dedicated Green CHIPS community spending. The full regional community fund is a separate $500 million partnership involving Micron, the state and other partners. Whether portions overlap must be established before adding them together (Town of Clay host-agreement presentation; Green CHIPS fund).

Claims & figures

  • Projection$84.5M in payments over 49 years vs. $368.4M without the , for a $51.5B project scope — OCIDA, Oct. 2025
  • DocumentedFab 1 host arrangement: $20M over three years plus $10M Green CHIPS community spending — Town of Clay presentation
  • Documented$500M regional community investment fund — a separate partnership — ESD

More in Clay

4647 State Route 31 (Tax Map 045.-01-05.1, 044.-01-29.1, part of 045.-01-03.1)

Clay · Town Board

Northland Commons Mixed-Use PDD

4647 State Route 31 (Tax Map 045.-01-05.1, 044.-01-29.1, part of 045.-01-03.1)

Public HearingPublic record notes available
Apartments
446
Comm SF
92,000
Stories
4
Cost
$130M
LJB Companies, LLC / Derek C. Persse · Updated Nov 20, 2026
4708 Dey Road, Clay, NY 13090 (Tax Map No. 105.-02-02.1)

Clay · Planning Board

EquipmentShare Facility & Fuel Island

4708 Dey Road, Clay, NY 13090 (Tax Map No. 105.-02-02.1)

Public HearingPublic record notes available
Sq ft
—
Acreage
—
Cost
—
EquipmentShare.com Inc. · Updated Nov 17, 2026
4155 State Route 31, Clay, NY 13041 (Tax Map No. 028.-01-47.0)

Clay · Planning Board

Matthews Auto Group Redevelopment

4155 State Route 31, Clay, NY 13041 (Tax Map No. 028.-01-47.0)

Public HearingPublic record notes available
Sq ft
—
Stories
1
Cost
—
Matthews Auto Group · Updated Nov 17, 2026