-2026-28 Phase III: 147 mixed-income dwellings in two four-story mixed-use buildings and three two-story townhouse buildings at 927 S State St (parcel 095.-08-01.4), on 3.123 acres. Coordinated covers Phases III–XII, a separate broader scope of up to 1,563 dwellings and 1,843,920 residential gross SF. Architect page lists 147 multifamily apartments plus 20 townhouses, conflicting with municipal 147-total account and earlier 148-unit drawing. Approved unit schedule not obtained; do not infer 167. Staff recommends 116 affordable homes, 30 years from occupancy certification, equivalent materials and continued restrictions across ownership changes (proposed conditions until matched to final decision). SHA's compiled annual plan flags a $7M county contribution changing from cash to in-kind support and possible HUD-match issues; later resolution not verified.
Replaces aging public housing with 1,400 high-quality, energy-efficient mixed-income homes; 1-for-1 replacement guarantee; adds grocery, retail, and early education amenities reconnecting the South Side to Downtown Syracuse.
Staff / Agency Concerns
Multi-year disruption and phased resident relocation; coordination with heavy state DOT highway demolition work along the I-81 corridor.
Public Testimony
Broad civic and municipal support; strong tenant advocacy focused on binding displacement protections, right-to-return enforcement, and job training for neighborhood residents.
Earlier record notes · source attribution pending
Older entries may combine applicant, agency, board and public comments. They are not classified as verified testimony.
Replaces aging public housing with 1,400 high-quality, energy-efficient mixed-income homes; 1-for-1 replacement guarantee; adds grocery, retail, and early education amenities reconnecting the South Side to Downtown Syracuse.
Multi-year disruption and phased resident relocation; coordination with heavy state DOT highway demolition work along the I-81 corridor.
Broad civic and municipal support;
Citizen / hearing feedback:strong tenant advocacy focused on binding displacement protections, right-to-return enforcement, and job training for neighborhood residents.
The story behind it
Researched Oct 7, 2026 · Medium confidenceSupported by public records, with some gaps or single-source details.
East Adams Phase III proposes 147 homes and commercial space at 927 South State Street. Its site-plan application is distinct from the much larger environmental review covering future phases, and the final approval conditions remain unconfirmed.
History
The August 10 city packet identifies Phase III as two four-story mixed-use buildings and three two-story townhouse buildings on 3.123 acres, parcel 095.-08-01.4. Its staff report records a prior subdivision approved October 21, 2024 and a July 15, 2026 county referral. The July 30 hearing notice schedules an August 10 hearing for the phase site plan and coordinated Phases III–XII . The broader environmental scope includes up to 1,563 dwellings, approximately 1,843,920 residential gross square feet, 22,000 square feet of grocery space and 28,700 square feet of other retail; these are not Phase III quantities. Earlier public program descriptions use different neighborhood-wide totals. Secondary reporting describes a conditional Phase III approval, but the adopted decision and enforceable relocation instruments were not obtained. The September 2025 application names East Adams Phase III, L.P. as the contracted developer, expressly distinguishing it from owner Syracuse Housing Authority. Its attached December 3, 2024 letter bears the signatures of Michael Saunders for the partnership and William Simmons for SHA, authorizing site access and a potential environmental easement. That permission is not a deed transfer or proof of awarded tax credits.
Who's involved
Owner identified in city staff report; current deed not independently retrieved
Syracuse Housing Authority
Applicant/development partner identified in packet
McCormack Baron Salazar
Architect and municipal-review representative
Ashley McGraw Architects
Engineering consultant on June 1 drawing
Langan
Neighborhood initiative partner; not equated with parcel owner
Blueprint 15
Resident-services partner identified in city grant announcement
Urban Strategies Inc.
Brownfield requestor and contracted developer according to applicant filing; not property owner
East Adams Phase III, L.P.
General partner named in brownfield certification; ownership roster not established
East Adams Phase 3 GP, Inc.
Partnership vice president signing site-access letter; role is not proof of equity ownership
New York State Department of Environmental Conservation
Tax-credit amount not established
September 2025 applicant filing identified; executed cleanup agreement, completion certificate, credit eligibility and actual credits not verified
Claims & figures
Projection116 of the 147 units are proposed as affordable for at least 30 years; city certification and restrictions are discussed as approval conditions. An executed obligation was not obtained. — August 10, 2026 city staff report
ProjectionThe neighborhood plan describes one-for-one replacement of 672 public-housing units and return opportunities for eligible residents; the detailed legal protections require separate verification. — East Adams neighborhood plan and city grant announcement
Connections
The connection to I-81 is neighborhood geography and public infrastructure context, not evidence that highway money funds this phase. No additional common-owner project was established in the 34 projects, 13 businesses and four archived records examined.
Timeline
2024-07-17 — City announces neighborhood-wide HUD award$50 million; not a Phase III-specific award.
2024-10-21 — Prior subdivision approval cited by city staff; original decision not independently obtained.No figures reported.
2024-12-03 — SHA and development partnership sign brownfield site-access letter, subsequently included in application.No figures reported.
2025-09 — Brownfield application distinguishes SHA ownership from contracted development partnership.No verified tax-credit amount.
2026-06-01 — Applicant site drawing issued; not for construction.Parking table: 148 dwellings; retail figure 2,754 SF, not verified as final.
2026-07-15 — County planning referral reviews Phase III.147 dwellings, two commercial spaces, five buildings, 3.123 acres.
2026-08-10 — City hearing scheduled and review packet issued; this date alone does not prove adoption.147 dwellings; separate Phases III–XII environmental scope.
SUNY Upstate plans a $450 million state-funded hospital annex in Syracuse with a larger emergency department, burn and intensive care facilities, and operating rooms. Design began in 2025; the construction-management procurement was shortlisted in 2026. A construction start and opening date have not been established.